Levelling the playing field
![]() |
The Electrical Contractors' Association (ECA) has long maintained a view on what constitutes standard industry practice in contracting.
Its perspective is informed by enquiries from nearly 3,000 specialist contractors. ECA is therefore able to highlight ostensibly onerous practices within an industry where contracts can be unforgiving.
In the construction and facilities management sectors, clients attempt to dictate the terms and conditions upon which ECA Members are engaged to carry out their work.
There are two ways in which ECA Members are commonly asked to enter into contracts with their clients, namely:
- Modified standard form of contracts i.e. JCT or NEC.
- In-house bespoke terms and conditions which are procured as an investment in commercial risk protection by the client in question.
There are two reasons why modified standard forms or bespoke forms of contract come about:
- To recognise specific project risks, e.g. if the project is on a high security risk site, there may be additional contractual requirements surrounding security;
- Commercial risk transfer: in order to de-risk the commercial model of their own business, clients will often seek – either through standard form modifications or bespoke terms – to push as much commercial risk downwards within the contractual chain as possible.
The latter approach is intended to safeguard the profitability of their businesses, but it will often pass on unmanageable and overly onerous risk to the party carrying out the works.
ECA has published a guidance document that identifies common areas of standard form contracts (which broadly represent the industry norm for what is acceptable risk allocation) and/or bespoke terms and identifies where those issues are modified to an ECA Member’s detriment.
The document also outlines the risk of those types of clauses; it suggests a risk-proportionate approach and rationale for finding and negotiating a compromise which aligns the risks involved with the parties who are realistically and proportionately in a position to manage those risks.
ECA wishes to identify and inform the engineering services sector and ECA Members’ decisions on what ‘fair, reasonable and good contractual practice’ looks like. ECA remains committed to fair and open competition and this document is not designed in any way to dictate what may be an appropriate risk allocation for a specific project, or act as a substitute for ECA Members obtaining project and context-specific legal advice.
ECA Members can click here to view ECA guidance on what are considered onerous contractual practices and how to handle them.
[edit] About this article
This article was written by Rob Driscoll, ECA Director of Legal and Business. It was previously published on the ECA website in August 2019 and can be accessed here.
[edit] Related articles on Designing Buildings Wiki
- Bespoke construction contract
- Complex project.
- Concession Contracts Regulations.
- Constructing Excellence contract
- Contract documents for construction
- Core clause.
- Intermediate building contract
- JCT
- JCT Construction management contract
- Modifying clauses in standard forms of construction contract
- NEC Option A: Priced contract with activity schedule
- NEC3
- Non-performance.
- PPC 2000
- Procurement plan.
- Procurement route
- Procurement team
- Risk allocation.
- Standard form of contract
- Traditional contract for construction
- Traditional contract: tender
- Typical tender process for construction projects
--ECA
Featured articles and news
How can digital twins boost profitability within construction?
A brief description of a smart construction dashboard, collecting as-built data, as a s site changes forming an accurate digital twin.
Unlocking surplus public defence land and more to speed up the delivery of housing.
The Planning and Infrastructure bill oulined
With reactions from IHBC and others on its potential impacts.
Farnborough College Unveils its Half-house for Sustainable Construction Training.
Spring Statement 2025 with reactions from industry
Confirming previously announced funding, and welfare changes amid adjusted growth forecast.
Scottish Government responds to Grenfell report
As fund for unsafe cladding assessments is launched.
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Architects Academy at an insulation manufacturing facility
Programme of technical engagement for aspiring designers.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Building Engineering Business Survey Q1 2025
Survey shows growth remains flat as skill shortages and volatile pricing persist.