Levelling the playing field
The Electrical Contractors' Association (ECA) has long maintained a view on what constitutes standard industry practice in contracting.
Its perspective is informed by enquiries from nearly 3,000 specialist contractors. ECA is therefore able to highlight ostensibly onerous practices within an industry where contracts can be unforgiving.
In the construction and facilities management sectors, clients attempt to dictate the terms and conditions upon which ECA Members are engaged to carry out their work.
There are two ways in which ECA Members are commonly asked to enter into contracts with their clients, namely:
- Modified standard form of contracts i.e. JCT or NEC.
- In-house bespoke terms and conditions which are procured as an investment in commercial risk protection by the client in question.
There are two reasons why modified standard forms or bespoke forms of contract come about:
- To recognise specific project risks, e.g. if the project is on a high security risk site, there may be additional contractual requirements surrounding security;
- Commercial risk transfer: in order to de-risk the commercial model of their own business, clients will often seek – either through standard form modifications or bespoke terms – to push as much commercial risk downwards within the contractual chain as possible.
The latter approach is intended to safeguard the profitability of their businesses, but it will often pass on unmanageable and overly onerous risk to the party carrying out the works.
ECA has published a guidance document that identifies common areas of standard form contracts (which broadly represent the industry norm for what is acceptable risk allocation) and/or bespoke terms and identifies where those issues are modified to an ECA Member’s detriment.
The document also outlines the risk of those types of clauses; it suggests a risk-proportionate approach and rationale for finding and negotiating a compromise which aligns the risks involved with the parties who are realistically and proportionately in a position to manage those risks.
ECA wishes to identify and inform the engineering services sector and ECA Members’ decisions on what ‘fair, reasonable and good contractual practice’ looks like. ECA remains committed to fair and open competition and this document is not designed in any way to dictate what may be an appropriate risk allocation for a specific project, or act as a substitute for ECA Members obtaining project and context-specific legal advice.
ECA Members can click here to view ECA guidance on what are considered onerous contractual practices and how to handle them.
[edit] About this article
This article was written by Rob Driscoll, ECA Director of Legal and Business. It was previously published on the ECA website in August 2019 and can be accessed here.
[edit] Related articles on Designing Buildings Wiki
- Bespoke construction contract
- Complex project.
- Concession Contracts Regulations.
- Constructing Excellence contract
- Contract documents for construction
- Core clause.
- Intermediate building contract
- JCT
- JCT Construction management contract
- Modifying clauses in standard forms of construction contract
- NEC Option A: Priced contract with activity schedule
- NEC3
- Non-performance.
- PPC 2000
- Procurement plan.
- Procurement route
- Procurement team
- Risk allocation.
- Standard form of contract
- Traditional contract for construction
- Traditional contract: tender
- Typical tender process for construction projects
--ECA
Featured articles and news
Cladding remediation programmes, transparency and target date.
National Audit Office issue report on cladding remediation.
HBPT and BEAMS Jubilees. Book review.
Does the first Labour budget deliver for the built environment?
What does the UK Budget mean for electrical contractors?
Mixed response as business pays, are there silver linings?
A brownfield housing boost for Liverpool
A 56 million investment from Homes England now approved.
Fostering a future-ready workforce through collaboration
Collaborative Futures: Competence, Capability and Capacity, published and available for download.
Considerate Constructors Scheme acquires Building A Safer Future
Acquisition defines a new era for safety in construction.
AT Awards evening 2024; the winners and finalists
Recognising professionals with outstanding achievements.
Reactions to the Autumn Budget announcement
And key elements of the quoted budget to rebuild Britain.
Chancellor of the Exchequer delivers Budget
Repairing, fixing, rebuilding, protecting and strengthening.
Expectation management in building design
Interest, management, occupant satisfaction and the performance gap.
Connecting conservation research and practice with IHBC
State of the art heritage research & practice and guidance.
Innovative Silica Safety Toolkit
Receives funding boost in memory of construction visionary.
Gentle density and the current context of planning changes
How should designers deliver it now as it appears in NPPF.
Sustainable Futures. Redefining Retrofit for Net Zero Living
More speakers confirmed for BSRIA Briefing 2024.
Making the most of urban land: Brownfield Passports
Policy paper in brief with industry responses welcomed.
The boundaries and networks of the Magonsæte.